Palletizing System RFQ Checklist: What to Specify Before Requesting Quotes
Prepare a palletizing RFQ with product, throughput, pallet, site, interface, supply and acceptance fields, then copy, print or export your draft.
A useful palletizing RFQ gives every supplier the same operating case and the same supply boundary. Record the packs, required output, pallet loads and site conditions before comparing proposals. Use the editable worksheet below to collect the information; it does not select a robot or validate a cell design.
Fill the requirements before naming equipment
Ask production to confirm the pack range and demand, engineering to confirm the layout and interfaces, and the project owner to assign the scope. Put an owner and a due date beside unconfirmed information. An empty value should remain visibly unresolved rather than becoming a supplier assumption that nobody reviews.
The form runs in your browser. You can print it, copy its contents or export a CSV to send through your own channels. Filling it in does not submit an enquiry or upload the answers. Export your draft before refreshing or closing the page. The worksheet is a project discussion aid, not a machine specification approved by an engineer.
Seven groups of RFQ inputs
| Group | Record | Ask the supplier to return |
|---|---|---|
| Product | SKU list; minimum, nominal and maximum dimensions and mass; surface, closure and handling limits | Proposed handling method, trial-sample requirements and any excluded pack variants |
| Throughput | Good-output target, normal and peak demand, operating time, product sequence and counting boundary | Rate assumptions, included interruptions and the proposed test method |
| Pallet | Pallet drawing and condition, layer pattern, load limits, consumables and exchange method | Pattern restrictions, pallet-quality assumptions and exchange responsibilities |
| Site | Usable layout, clear height, access, utilities, environment and installation window | Layout, utility requirements, access needs and site work excluded from supply |
| Upstream and downstream | Infeed presentation, outfeed destination, signals, identification and exception handling | Mechanical and control interfaces with a named party at each handover |
| Supply boundary | Equipment, engineering, installation, documents, software, training and support | Included, optional, excluded and buyer-supplied items listed separately |
| Acceptance | Representative products, measurable criteria, FAT/SAT allocation, witnesses and closeout | Proposed tests, evidence, responsibilities and unresolved conditions |
Make the rate measurable
“Packs per minute” needs a counting point and a time basis. A rate at the robot pickup position does not establish how many accepted pallets leave the line during a shift. Include pallet exchange, replenishment and product changeovers in the discussion, and state which of them belong in each test.
For an assumed example, a site needs 600 good packs during a 30-minute observation that includes pallet exchanges. Its requirement is 20 good packs per elapsed minute for that observation. That arithmetic describes demand; it does not prove a proposed machine can meet it. Record product mix and pack orientation alongside the calculation. Use the throughput calculation guide for the separate capacity discussion.
Draw the supply boundary
Ask who supplies empty pallets, takes full pallets away, provides pack identification and connects the controls. Mark existing equipment on the layout. A conveyor, pallet dispenser or wrapper can sit outside one supplier’s quotation while remaining necessary to the project.
ISO 10218-2:2025 addresses industrial robot applications and cells, including integration. Its published scope supports treating the assembled application as a project responsibility. A robot quotation alone does not describe that responsibility. Ask the integrator which requirements apply to the proposed application and what supporting documents will be supplied.
Attach evidence and control revisions
Keep drawings, SKU data and photographs in a separate attachment list with filenames and revisions. The form does not upload files. Ask for trial quantities using the actual product and pallet range, including the variants the supplier considers difficult. Record sample availability rather than promising a test that cannot be staged.
Give each RFQ issue a date and revision. When a dimension or layout changes, send the same revision to every bidder and ask them to identify the effect on scope and price. Use the project cost guide to reconcile exclusions and the FAT/SAT planning guide to agree evidence before the order.
Prepare your draft for supplier review
Check units, unresolved fields, attachment revisions and named owners before exporting. Keep supplier answers next to the original requirement so that a qualified response is visible. The buying guides connect this RFQ to budget, acceptance and maintenance planning; the editable worksheet follows this article.
Build your palletizing RFQ
Fill in what you know; leave unknowns blank. Answers stay in this page and are not uploaded. Export before reloading or closing.
Sources and scope
Source dates refer to the material consulted, not independent performance verification.
- ISO 10218-2:2025: Industrial robot applications and robot cells
Published scope covers integration of robot applications and cells; catalog scope only, not a full-standard compliance review.
Second edition, 2025-02 · Checked October 6, 2026 - IEC 62381:2024: Automation-system acceptance testing
Public scope describes specification-based factory/site acceptance and project-specific responsibilities; process-industry scope is stated.
Edition 3, 2024-07-30 · Checked October 6, 2026
Published by DeltaSpark. Editorial policy · Corrections and contact
Continue reading
FAT and SAT Planning for Packaging Automation Projects
Prepare a project-specific FAT and SAT matrix covering products, output, interfaces, evidence, deviations and handover for packaging automation.
Read articleMaintenance Planning for a Robotic Palletizing Cell
Plan palletizing-cell maintenance with an asset register, model-specific documents, spares, support ownership and handover records before production starts.
Read articlePalletizing System Cost: What a Complete Project Budget Should Include
Build a palletizing project budget that includes tooling, integration, site work, commissioning and operating costs without relying on generic price ranges.
Read article