FAT and SAT Planning for Packaging Automation Projects
Prepare a project-specific FAT and SAT matrix covering products, output, interfaces, evidence, deviations and handover for packaging automation.
Agree what will be tested at the supplier’s factory, what must wait for the installed site, and what evidence will close each requirement before the equipment order. A FAT can demonstrate an agreed configuration under factory conditions. A SAT addresses the installed configuration and the site conditions included in the contract. Neither label by itself defines a pass result.
The matrix below is an editorial starting point for a packaging-automation project. Set the applicable requirements with the supplier, integrator and site team; do not treat the proposed rows as universal acceptance criteria.
Freeze the basis of the test
Record the requirement revision, drawings, software and recipe versions, product samples, pallet types and connected equipment. State which parts of the line are real and which are simulated. An emulated downstream-ready signal may support a factory control check, but it leaves the physical handover to the installed downstream machine untested.
IEC 62381:2024 describes factory and site acceptance and integration testing against an applicable specification. Its published scope concerns automation systems in the process industry and includes adapting plans to the project. We use that distinction as background; the table here is our discussion template, not a reproduction of its checklists or a claim of compliance.
Allocate tests to the place that can prove them
| Item to discuss | Possible factory evidence | Site evidence or open point |
|---|---|---|
| Product handling | Agreed samples run with the nominated tooling and recipes | Confirm actual incoming variation and connected-line presentation |
| Output | Good-output count with time basis, interruptions and configuration recorded | Confirm the agreed integrated operating case with actual supply and removal |
| Pallet load | Pattern, orientation, height and damage observations against agreed criteria | Confirm pallet range and the nominated transfer to downstream handling |
| Changeover | Agreed format changes with tasks and time boundary recorded | Confirm site roles, access, recipe control and required materials |
| Interfaces | Signal list, simulated conditions and witnessed responses | Actual upstream/downstream, identification and data connections |
| Abnormal conditions | Agreed, controlled test cases designed by the responsible engineers | Site-specific cases and documented recovery responsibility |
| Safety-related verification | Reports and outstanding validation items from the responsible integrator | Verification appropriate to the final installed application |
| Documentation and training | Draft manuals, drawings, software/configuration records and training plan | Final revisions, delivered training, access and handover records |
A successful production run is not a substitute for safety validation. ISO 10218-2:2025 addresses industrial robot applications and cells, including integration. Have the responsible specialists define the validation work for the actual application.
Write an observable pass statement
Give every requirement an identifier, test method, measured quantity, acceptance limit, witness and evidence location. Agree how a failed sample, planned interruption or retest affects the result. Leave an unknown limit open for approval rather than copying a number from another installation.
An assumed example illustrates the counting issue: 240 accepted packs observed over 12 elapsed minutes equal 20 good packs per elapsed minute. If someone excludes two minutes of pallet exchange, the same count becomes 24 per counted running minute. Both calculations are arithmetically valid; they answer different questions. Agree the denominator before the test, and report both if both matter. These figures are not a capacity claim or a recommended acceptance threshold.
For load quality, specify what will be inspected and against which drawing or agreed sample. For changeover, define the starting and ending conditions. For data exchange, retain the relevant records and identify the receiving system. “Works correctly” leaves each of those decisions open.
Close deviations without losing their history
Use an issue log with the requirement ID, observation, evidence, responsible owner, action, due date and retest result. Agree which unresolved items prevent shipment, which prevent site acceptance and which can remain under an explicitly approved action plan. The contract and project risk assessment determine those decisions.
If the configuration changes after a test, identify the affected results and decide what must be repeated. Keep the original results rather than replacing them with a clean table. A signed cover sheet should point to the actual reports, software revisions and unresolved items.
Prepare for handover
Before the review, gather the RFQ revision, product and pallet list, interface schedule, test matrix, trial materials and witness availability. Allocate responsibility for providing samples and arranging the site operating window. Use the RFQ worksheet to capture those inputs and the maintenance planning guide to define what the receiving team needs.
Keep commissioning costs and retest responsibilities in the project budget. The buying-guides hub links the planning documents used before and after acceptance.
Sources and scope
Source dates refer to the material consulted, not independent performance verification.
- IEC 62381:2024: Automation-system acceptance testing
Public scope describes specification-based factory/site acceptance and project-specific responsibilities; process-industry scope is stated.
Edition 3, 2024-07-30 · Checked October 6, 2026 - ISO 10218-2:2025: Industrial robot applications and robot cells
Published scope covers integration of robot applications and cells; catalog scope only, not a full-standard compliance review.
Second edition, 2025-02 · Checked October 6, 2026
Published by DeltaSpark. Editorial policy · Corrections and contact
Continue reading
Maintenance Planning for a Robotic Palletizing Cell
Plan palletizing-cell maintenance with an asset register, model-specific documents, spares, support ownership and handover records before production starts.
Read articlePalletizing System Cost: What a Complete Project Budget Should Include
Build a palletizing project budget that includes tooling, integration, site work, commissioning and operating costs without relying on generic price ranges.
Read articlePalletizing System RFQ Checklist: What to Specify Before Requesting Quotes
Prepare a palletizing RFQ with product, throughput, pallet, site, interface, supply and acceptance fields, then copy, print or export your draft.
Read article